As many of you may have heard we are moving to a large location
The fun will start on june 15 this month when we get our hands on a new set of keys

demo and build out of the show room should take us about three weeks, building of stands and tanks should take us another two weeks! plumbing and finishing should take us to the first week of aug
so for the current location will be closed as of first week of july to allow us enough time to work in the new location.
here is the rough plans i have set out for the guys to finish up
hoping to be open sept 1 with a grand opening sale and door prizes
Thanks Dave
ps if anyone is interested in some demo store tanks we will blowing out all the current ones we are using for cheap lol